    Lake Shore Central School District Capital Construction Project: Phase 2

    The District is gearing up for Phase 2 of its Capital Construction Project, set to begin in January. Phase 2 will involve a new traffic pattern at the Middle School (click HERE for detailed information and map) while the school's main entry, main office and nurses' office areas are reconstructed and a secure entryway is installed. There also will be an expanded restroom area near the auditorium. This work is expected to be completed by Fall.
    Phase 2 also brings additional work at the High School, where students have attended since the 1950s. Work will start in mid-January on an athletic entrance with a concession area and indoor restrooms for athletic events (see illustrations above), as well as the construction of technology classrooms.

    The four-phase Capital Construction Project was appoved by voters in May 2017 after a facilities study identified numerous areas in an end-of-life state that reequired attention to maintain the safety and integrity of district buildings.

     
    KEY PROCESS DATES
    Wednesday 12/18 10:00 Bid Opening @ Hoag.  Follow up meeting afterwards to review and discuss bids, alternates, budget etc. 
    Thursday-Friday  12/19-12/20—Contractor Descoping meetings
    Monday 12/23 (tentatively), Might be Friday, 1/3—Contract recommendations to the District Proposed 
    Wednesday 1/8  4:00 pm at the High School — Special BOE Meeting to approve contracts