Capital Project
Lake Shore Capital Project · Phase 2
Phase 2 is underway. New turf fields, lights for night games, and air conditioning and new lighting in High School classrooms: better places to learn, play and come together, for every Lake Shore student.
Progress
Site prep and demolition
Old bleachers and concession stand removed
Done
Grandstand and two-sided press box
1,044 seats, press box with streaming capability
Done
LED field lighting
New lights for night games
Done
Turf fields
Multi-sport field plus baseball and softball, with new dugouts and backstops
Underway now
High School air conditioning and classrooms
Full A/C, new ceilings and LED lighting, phased over summers
Ongoing
Full completion
Summer 2027
What Phase 2 brings
Athletics
Multi-sport turf: 225' x 360' fields with custom graphics for soccer and lacrosse.
Turf diamonds: turf baseball and softball fields with new dugouts and backstops.
Grandstand: 1,044 seats and a two-sided press box with streaming capability.
Night games: LED field lighting and new scoreboards.
Lake Shore High School
Air conditioning: year-round climate control throughout the High School.
Learning spaces: new ceilings and high-efficiency LED lighting in classrooms.
Planned around school: work is phased over several summers to keep the school year on track.
Phase 2 site plan, from the start of the project. Dates shown were early estimates.
How it's paid for
Phase 2 is part of a multi-year plan funded by state building aid, expiring debt service and voter-approved reserves. It does not raise taxes.
Project updates
Oct 2026
Rolls of new turf have arrived, and crews are installing it across the new athletic fields.




Oct 2, 2026
The grandstand, press box and LED field lights are finished. Families and students filled the new seats for Homecoming.

June 3, 2026
Crews put up the main framework for the new grandstand. It turned an open site into a place our community will gather for years.
May 18, 2026
After one of the wettest Aprils on record, crews poured the concrete pads that hold up the new seating and press box. Work on the playing surfaces continued alongside.



April 14, 2026
Cranes and rigging crews installed the new high-efficiency LED light poles at the stadium.
March 30, 2026
Crews took down the old concession stand to make room for the new grandstand and facilities.


March 16, 2026
Generations of Lake Shore families cheered from the original home-side bleachers. Taking them down started the groundwork for the new grandstand.


Feb 17, 2026
Lake Shore leaders, led by Superintendent Phil Johnson, picked up sledgehammers instead of shovels to start Phase 2.